University of Oregon

Autzen Stadium Expansion & Renovation

Executive Summary - Financial Data


Project: Expansion and renovation of University of Oregon Autzen Stadium including:

  • Addition of more than 12,000 seats, increasing seating capacity to 53,800
  • Increased accessibility
  • Improved food service and restroom facilities
  • Chair-back seating (5,000 seats)
  • 32 additional Private Sky Suites
  • Construction: Funding: Financing: Private gift fund-raising/naming rights may be paid over a ten-year period. New seat and Private Sky Suite assessments are payable over a five-year period. Financing up to a maximum of approximately $20 million may be required. Borrowed funds will be repaid during the ten-year period that gifts are received. Payment will be a maximum of approximately $2.5 million per year.

    Financing Scenario:

    Cash Flow (in millions)
    Construction Years Years
    Revenue Source 2 years 3-6 7-12 Total
    Major Gifts Committed $53.0                    $  53.0
    Fund Raising - Naming $  2.3 $  5 $  7.7 $  15.0
    Assessments $  2.5 $  7.5           $  10.0
    Additional Seats/price inc $  2.5 $18.0 $27.0 $  47.5
    Financing $19.7                         $  19.7
    Sub-total $80.0 $30.5 $34.7 $145.2
    Construction/Debt Service ($80) ($10.0) ($15.0) ($105.0)
    Total 0 $20.5 $19.7 $  40.2

    Future Athletic Department needs: Future revenue from Autzen Stadium expansion will be used to meet the following Athletic Department Needs: