ALLEN HALL
RENOVATION
Rapid growth of the student body and faculty in the School of Journalism and
Communication, along with escalating needs for specialized classrooms and resource
facilities, has triggered the need to renovate Allen Hall. Planning for the
complete renovation of Allen Hall was based on a November 13, 1995 master plan
study by Boucher Mouchka Larson Architects (BML). Phases I and II were completed
in earlier years. Total project budget: $3.5 million.
ALLEN HALL RENOVATION PHASE III - RESOURCE ROOM
Interior
Photo, Exterior Photo
Size: approximately 1,400 sf remodeling (1 floor)
Total Project Budget:
approximately $373,000 private funds (Direct construction $282,000)
Architect:
Boucher Mouchka Larson Architects (BML), Portland
Construction Firm: Morris
P. Kielty, Eugene
Project Manager: Alex Gordon
Project Planner: Chris
Ramey
This phase created a Resource Room (Willis S. Dunaway Journalism Resource Room), which provides new space designed for study, meetings, and student research. As the School's curriculum increasingly becomes project-oriented with strong emphasis on team and individual projects, space is needed for student meetings and team conferences, and students need greater access to computers and computer networks. The Resource Room meets all of these needs. In addition, a schematic design for a new entry was completed. Construction was completed in Spring 1999.
ALLEN HALL RENOVATION PHASE IV
Exterior Photo 1, Interior Photo
Size: approximately
1,100 SF addition (1 & 2 floors)
Total Project Budget: approximately $850,000
private funds
Architect: Boucher Mouchka Larson Architects (BML), Portland
Landscape Architect: Cameron McCarthy Gilbert, Eugene
Construction Firm:
Morris P. Kielty, Eugene
Project Planner: Chris Ramey
Project Manager:
Alex Gordon
This phase included the creation of a new 1,100 SF building
entry which efficiently connects the two portions of the lower floors with each
other and with the rest of the building. Additionally, because the ground floor
of the building is below grade, an entry plaza was designed to adjust from the
surrounding grade to the entrance level through a series of gradual transitions
to the existing contours.
Phase IV included a conference room devoted
to alumni recognition and the Dean's Complex, consisting of a two-room Dean's
suite with private office, staff office and support area. Construction began
in Summer 1999 and was completed in April 2000.
ALLEN HALL RENOVATION, Phase V
Size: approximately 21,700
gsf remodeled space
Total Project Budget: approximately $2,000,000 in mostly
gifts, but also including $561,800 in G-bonds.
Architect: Boucher Mouchka
Larson Architects (BML), Portland, OR, (503) 223-4886
Construction Firm: DPR
Construction, Eugene, OR, (541) 341-1329
Project Planner: Chris Ramey, (541)
346-5562
Project Manager: Alex Gordon, (541) 346-5219
Description: This phase made improvements to the second and third floors including conversion of the resource room to an electronic classroom and conversion of the old Dean's office to faculty offices.
Status:
Construction completed Fall 2001.
Location: Autzen Stadium
Size: approximately 12,000 new seats and
renovation.
Total Project Budget: $89.7 million ($72 million direct construction)
Architect: Ellerbe Becket, Kansas City, MO (816) 561-4443
Construction Firm: Hunt/Wildish, Eugene (541) 485-1700
Project Planner: Chris Ramey, (541) 346-5562
Project Manager: Charlene Lindsay, (541) 346-5276
Description: The stadium expansion design addressed the need to expand seating capacity and the need to improve circulation, accessibility, restrooms, concessions, and press facilities. It took into consideration the original design by Skidmore, Owings, and Merrill, which displays axial geometry, symmetrical massing, easily understood circulation, and the use of the berm as a podium for the stadium. The phased expansion and renovation project added 12,000 new seats, 3,000 of which are located in a new covered "club section," along with 32 new skyboxes, a three-story luxury suite, and improved concession stands. These improvements are expected to produce more revenue, thus helping the athletic department to become completely self-funding. The total stadium capacity increased from 41,700 to 53,800 seats.
The site master plan addressed the need for improved circulation, parking, transit capacity, accessibility, and pre-game activity amenities (including new restroom facilities).
The schematic design was completed in winter 2000. Phase 1 of the project, including landscaping of the north berm, was completed in 2000. Phase 2, including new artificial turf; the new bus transit station; new water, sewer, and electrical facilities; new ticket booths; and a decorative fence around the stadium, was completed in summer 2001. Phase 3, including the addition of 12,000 new seats, improved restrooms, concessions, and walkways, were completed before the 2002 football season. Phase 4, including the addition of new sky suites and pressbox, was finished by the 2003 season.
Status: Completed summer 2003.
CAMPUS DEVELOPMENT PROJECT
Faced with the twin challenges of increased numbers of students and outmoded
classroom facilities, the university embarked on a three-phase project to expand
and modernize core academic space on the campus. Stage One (see William
W. Knight Law School) of the project relocated the Law School to a new building
on land available at the eastern edge of the campus periphery (completed), freeing
up the central campus space of the previous Law building (McKenzie Hall) for
general educational uses. The renovation of McKenzie Hall, Stage Two (see McKenzie
Hall Renovation), is also completed. Stage three of the project is the Lillis
Hall/Gilbert Hall Additions and Alterations Project. Lilles Hall was completed
in winter 2004
Project Planner: Christine Thompson, (541) 346-5572
The purpose of diagnosis studies is to record the existing conditions of the campus as they relate to the university's Long Range Campus Development Plan's policies and patterns. These studies aid in decision making for potential development of the area, as well as help identify the need for future amendments to the Long Range Campus Development Plan.
For more
information click here.
Status: Completed.
Project Planners: Chris Ramey, (541) 346-5562 and Christine Thompson, (541) 346-5572
The University of Oregon began the process of updating its Campus Plan (previously known as the 1991 Long Range Campus Development Plan) in the summer of 2004.
The Campus Plan describes the guiding principles (or patterns) and policies that define the type and extent of future campus development. The 1991 LRCDP was written nearly fifteen years ago. It has effectively guided the university through an active period of development and improvements resulting in a noticeably enhanced campus environment. Change happens incrementally, making an overall guiding plan essential. The plan's basic precepts remain very effective. Nonetheless, it is important to revisit portions of the LRCDP to evaluate potential improvements to the planning process and to fix outdated information. These efforts will ensure that the LRCDP will serve the campus for the next ten years.
A draft updated Campus Plan was completed and reviewed by a wide body of individuals and groups during a three-month time period beginning January 11, 2005 and ending with the CPC April 12, 2005 public hearing. The Campus Planning Committee reviewed the comments and suggestions gathered during this review period prior and took action May 24, 2005. The CPC's recommendation for approval was supported by university administration.
Click here to see the updated Campus Plan.
Status: Completed
Project Planner: Christine Thompson, (541) 346-5572
Description: The purpose of the Campus
Outdoor Lighting Plan is to interpret and enhance the existing Long Range
Campus Development Plan (LRCDP) outdoor lighting policies creating a Level 3
Plan. The plan defines lighting parameters for entrances, pedestrian walkways,
and parking lots on campus. It also describes review requirements and defines
the campus standard light fixture design.
Outdoor lighting on campus has received a great deal of attention over the years.
This plan is designed to address the key issues and concerns surrounding the
subject. Establishing a plan (in particular prioritizing outdoor lighting walkways)
will also allow the CPC to review outdoor lighting improvements in a comprehensive
manner, thus eliminating the need for individual lamp location reviews.
Status: Completed winter 2004.
CAMPUS TREE PLAN
Project Planner: Christine Thompson, (541) 346-5572
The Campus Tree Plan, created by the Campus Planning Committee, will guide future care for the trees on campus to ensure that they remain a vital component of the campus environment. The university has had in place other policies (Long Range Campus Development Plan) which address tree management, but the policies lacked specificity and were not comprehensive. The new Campus Tree Plan ensures that all development, repair, maintenance and operations of the University of Oregon campus incorporate tree management principles addressing tree protection, tree replacement, landscape design, and environmental sustainability.
The Campus Tree Plan became available in October, 2001.
EAST CAMPUS
(MOSS STREET) CHILDREN'S CENTER
Location: East Campus
Size: 13,500 sf
Total Project Budget: approximately $2.8 million
Architect: Mahlum Architects, Portland, OR, (503) 224-4032
Construction Firm: Ordell, Springfield, OR, (541) 747-8734
Project Planner: Dorene Steggell, (541) 346-5606 Project Manager: George Bleekman,
(541) 346-2625
This 2.8 million dollar 13,500-square-foot project replaced the former Child Care and Development Center facilities occupying houses in East Campus and the EMU. The new Center serves approximately 120 children, infants through school-aged, of university students, faculty, and staff. The Center has many sustainable aspects, including daylighting, and ground-source heat pumps.
Status: The grand opening was held in May 2004. [updated 1/05]
EAST CAMPUS DEVELOPMENT POLICY UPDATE
Project Planners: Chris Ramey, (541) 346-5562 and Christine Thompson, (541) 346-5572
The university, with input from neighbors and campus community members, created a new policy for East Campus development. The policy's goal is to provide for the expansion of the institution, based on its needs, without diminishing the quality of the surrounding neighborhood. It describes the type and extent of future development in the East Campus Area. The policy addresses the following key elements: university mission, graceful edges, campus-like character, traffic, parking, maintenance, and communication.
Click here for more information about the project.
Status: The project was completed Fall 2004.
Sketches: Goal 1, Goal 2, Goal 3, Goal 4
Landscape Architect: Cameron McCarthy
Gilbert & Scheibe, Eugene, along with the consulting firm of Moore, Iacofano,
and Goltsman (MIG), Eugene.
Project Planner: Dorene Steggell
This project is one of a series of projects that looks at ways to improve campus
gateways. Well-developed entrances to the campus increase coherency and create
a sense of the campus as a definable space. The Eastgate project covers the
area between Oregon Hall and the University Health and Counseling Center and
its surroundings. This area is particularly important because it is the first
point of arrival for prospective students, staff, faculty, and campus visitors.
It also is a key component of the university's vehicular circulation system.
A steering committee was established
and worked with the landscape architecture firm on the Feasibility Study. A
workshop was held February 5, 1999 to gain input from a broader focus group.
The results of this meeting were presented at a campus-wide presentation.
The Feasibility Study report, completed August 1999, identified four conceptual goals: (1) sense of arrival, (2) traffic control, (3) reflection of the Oregon landscape, and (4) front doors to buildings.
(COLLEGE OF)
EDUCATION CONCEPTUAL DESIGN
Size: approximately 94,000 gsf new construction and 17,000 gsf alterations
Total Project Budget: approximately $40 million
Architect: Zimmer Gunsul Frasca Partnership, Portland, OR, (503) 224-3860
Project Planner: Chris Ramey, (541) 346-5562
Project Manager:
The College of Education is growing in response to a statewide need for effective teachers and school administrators and to substantial growth in research and service funding. The investment in physical facilities is essential to sustaining faculty productivity, program quality, and impact of faculty research and outreach services. Faculty, staff and students have been assigned to crowded, substandard, and/or remote structures. The recommended addition of 94,174 gsf of new space and renovation of 17,200 gsf of existing space will remedy current, serious space and functional problems and provide a modest increment for growth, if used prudently.
Status: The conceptual design is completed and fundraising is under way. [updated 12/03]
Size: approximately 213,000 gsf (three
floors)
Total Project Budget: approximately $200,000
Architect: MHTN Architects, Salt Lake City, UT, (801) 595-6700
Project Planner: Chris Ramey, (541) 346-5562
Since 1950, the Erb Memorial Union (EMU) has been the gathering place for campus activities at the University of Oregon. It houses more than 150 student groups and provides lounges, art galleries, a variety of food venues, a pool hall and arcade, a number of services, group meeting rooms, and a staff of program consultants to assist the student groups. The fifty-year-old building has undergone at least three additions or renovations during its lifetime.
This master plan contains a conceptual program for accommodating the EMU's space needs for the next 20 years, and a basic diagrammatic vision for how the needed space can be accommodated including identification of discrete construction phases which could be implemented over a number of years.
Status: The master plan is completed. [updated 12/03]
ERB MEMORIAL UNION
FOOD SERVICE & REC CENTER IMPROVEMENTS
The Fish Bowl Photo, The Buzz Photo, Rec Center Photo
Size: approximately 3,000 addition; 49,000
SF remodeled/renovated; (2 floors)
Total Project Budget: approximately $4,520,000 (Direct construction $3,224,000)
Architect: McBride/Seder Architects, Portland
Construction Firm: Wildish Building Co., Eugene
Project Planner: Fred Tepfer
Project Manager: Garry Fritz
This project remodeled the south and west
areas of the basement and ground floors of the Erb Memorial Union building.
Completed in the summer of 1998, it revised and improved circulation and visibility
in the Fishbowl and south dining room areas, restoring many circulation patterns
that were disrupted by the previous building addition and remodel. At the basement
level, the project added approximately 3,000 square feet, revising and clarifying
the corridors and circulation, and remodeling the Recreation Center and Quick
Copy. The Convenience Store also is now located in the remodeled space. The
new north addition, next to the current breezeway and with an entrance clearly
visible from 13th and University, contains a coffee house. Source of funds:
85% building fees; 15% state system utilities funds.
ERB MEMORIAL
UNION AMPHITHEATER
Size: courtyard
Total Project Budget: approximately $415,000 from incidental fees (Direct construction
$348,000)
Landscape Architect: Cameron McCarthy Gilbert & Scheibe, Eugene
Construction Firm:
Project Planner: Fred Tepfer
Project Manager: Garry Fritz
This project, completed in the summer of 1998, was initiated on behalf of the
ASUO by the 1996-97 ASUO President to commemorate the organization's 100-year
anniversary. The project repaired and improved the portion of the campus located
between the EMU and the intersection of 13th Avenue and University Street (approximately
24,000 SF). The landscape architect worked with a user group of students, faculty,
and staff. The project removed paving and some of the existing trees and constructed
a plaza near the intersection, one more suitable for large group gatherings
than the previous series of smaller spaces. It includes a raised "stage," and
all areas are accessible by gently sloping sidewalks that are more manageable
for people with disabilities. The project creates a more open view of the EMU
and also includes a clear path up to the main entrance of the building. This
project's support was due largely to enormous efforts on the part of the ASUO,
the user group, the consultant, and the general contractor working in very complementary
and productive ways. Source of funds: student incidental fees.
Size: elevator addition (1 floor)
Total Project Budget: approximately $555,000 - Student building fee financing
(Direct construction $351,000)
Architect: Robertson/Sherwood Architects, Eugene
Construction Firm: 2G Construction
Project Planner: Chris Ramey
Project Manager: Alex Gordon
This project, comprised of an elevator
in the Erb Memorial Union building, provides access to the International Student
Lounge, the Oregon Daily Emerald offices, and the Adell McMillan Art
Gallery. Construction was completed in Winter 2000.
fMRI FACILITY/STRAUB HALL ADDITIONS AND ALTERATIONS
Size: approximately 1,000 gsf addition
and 2,000 gsf remodel (one story)
Total Project Budget: $4,032,400 (includes $1,166,000 in G-bonds) for Straub
Hall alterations plus additional grant funds from fMRI grant application.
Architect: L. A. Kersh Architecture, Eugene, (541) 334-6408
Construction Firm: Hyland Construction, Springfield, OR, (541) 725-8081
Project Planner: Dorene Steggell, (541) 346-5606
Project Manager: George Bleekman, (541) 346-2625
Description: The Straub Hall Additions and Alterations Project, approved by the 1999 legislature, provides additional space for the Psychology Department. The project includes a small addition which houses the new fMRI facility, plus a remodel of adjacent existing space on the first floor of Straub Hall. The new Lewis Neuroimaging Center permits imaging of brain function and brain tissue that will allow scientists to better correlate the brain's anatomy with human thought and behavior.
Click here for Rendering of Hayward Plaza
Click here for Rendering of Hayward Plaza Entry
Location: Corner of Agate and 15th Streets
Total Project Budget: $950,000
Landscape Architect: Cameron McCarthy Gilbert Scheibe (541) 485-7385
Construction Firm: Brown Construction Company
Project Planner: Chris Ramey (541) 346-5562
Project Manager: Charlene Lindsay (541) 346-5276
The Hayward Plaza Project brings together two long-standing needs at this facility: creating a welcoming "front door" for the facility and providing an opportunity to recognize the great heritage of Hayward Field and the University of Oregon Track and Field programs.
This project will create a welcoming arrival point for Hayward Field as well as enhancing a significant campus entrance. The plaza project will incorporate displays telling the story of Hayward Field and our Track & Field programs. The design provides for access to these display areas for casual, weekday visitors as well as those attending events at the facility.
Status: Completed 2005.
Total Project Budget: approximately $690,000
Landscape Architect: Cameron McCarthy Gilbert Scheibe, (541) 485-7385
Construction Firm: Wildish Companies, (541) 485-1700/UO Landscape Students
Project Planner: Dorene Steggell, (541) 346-5606
Project Manager: Janet Lobue, (541) 346-5259
Construction is complete on the new Heart of Campus, which consists of replacement of the existing kiosk and the creation of a pedestrian-friendly plaza at the intersection of 13th Avenue and University Street. The project was funded by the sale of engraved bricks to commemorate the 125th anniversary of the University, and by the Department of Public Safety. The School of Architecture and Allied Arts and Facilities Services made significant in-kind contributions. The kiosk and surrounding areas were designed and constructed by UO Landscape students working with Professor Stan Jones. The street improvements were designed by Cameron McCarthy Gilbert Schiebe.
Status: Completed in fall 2004.
(LEE) KELLY
SCULPTURE
Total Project Budget: approximately $25,000
Engineering Consultant: MR Richards Engineering, Inc., Eugene
Project Planner: Dorene Steggell, (541) 346-5606
This project addressed the siting and installation of a large, donated sculpture titled Akbar's Garden by prominent Northwest artist Lee Kelly. The Straub Hall Quadrangle was selected by the artist and the donor as an appropriate site for the sculpture, which was installed there in June 2002.
(WILLIAM W.) KNIGHT LAW CENTER
Exterior
NW photo , Exterior
West , Interior
1, Interior 2,
Interior 3
Link
to Law Center's Blueprint tour and Factsheets
Size: 138,000 SF new construction (4 floors)
Total Project Budget: approx. $25 million - state bonds ($10.3 million) and
private gifts ($14.7 million). Direct construction $21,691,000
Architect: Yost Grube Hall, Portland
Construction Firm: Hoffman Construction Co., Portland
Project Planner: Chris Ramey
Project Manager: Janet Lobue
The new Knight Law Center at the corner of 15th Avenue and Agate Street was
the first stage of the Campus Development Project. The Law Center houses the
Law library and has boosted overall Law School space by almost 50% to accommodate
565 instruction stations, 41 faculty offices, and several administrative areas.
The new center better fits the way law is taught today, with more small classrooms
and seminar rooms, a student lounge, a moot courtroom, areas for groups to meet,
and access to the latest technology. It was designed by Portland architectural
firm Yost Grube Hall. The Law School moved in Summer 1999 when final construction
was completed.
LILLIS HALL/ GILBERT HALL ADDITIONS AND ALTERATIONS, PHASE THREE
Size: net additional square footage is
approximately 90,000 sf (four floors) plus replacement of 45,000 gsf (1952 Gilbert
bridge) and remodeling of 37,000 gsf (east and west buildings, three floors).
Total Project Budget: approximately $38.9 million - state "G" bonds ($3.45 million),
matching private gifts ($3.45 million), state "F" bonds ($100,000), and additional
gift funds from Lundquist College donors.
Architect: SRG Partnership, Portland, OR (contact: Hussain Mirza), (503) 222-1917
Construction Firm: Lease Crutcher Lewis, Portland, OR (CM/GC), (503) 223-0500
Project Planner: Fred Tepfer, (541) 346-5564
Project Manager: Janet Lobue, (541) 346-5259
The Lillis Hall/Gilbert Hall Additions and Alterations Project represents the
final stage of the Campus Development Project. It relieved some of the need
for general classroom space on campus.
The newly configured Lillis Business Complex, which houses the Lundquist College of Business in four separate, linked structures, connects the UO's west entrance to the Memorial Quadrangle. Its prominent location and Gilbert Hall's historic role as the first element of what became the Memorial Quadrangle (listed on the National Register of Historic Places) give it pivotal importance both on the campus map and in campus history.
This project is the first comprehensive addition and alteration project for Gilbert Hall in nearly 50 years. Since the center bridge connector (commonly referred to as the "Commonwealth Bridge") was opened in 1952, this building complex has been expanded and remodeled, but always without a comprehensive study of the long-range needs of the College of Business.
The project created a unified facility that fosters interaction among students and faculty and supports teaching and learning in the classroom, in self-directed teams, and in internships. It gives the College state-of-the-art teaching and support facilities, a new look and new front door onto the campus that it and the rest of the university can be proud of.
Structural
- Degenkolb Engineers; Mechanical/Electrical/Civil - Balzhiser & Hubbard Engineers;
Landscape Architect - Cameron, McCarthy, Gilbert & Scheibe; Life Safety
Ð Creighton Engineering.
Status: Construction of Lillis Hall was completed in late fall 2003. Planning
will begin in 2004 for renovation of the historic Gilbert (east) and Peterson
(west) wings. [updated 3/05]
Size: 3,500 square feet new construction
(one story)
Total Project Budget: approximately $1.2 million (student building fees and
gifts)
Architect: Jones & Jones Architects and Landscape Architects, Seattle, WA,
(206) 624-5702
Construction Firm: Preferred Construction Inc., Springfield, OR (541) 726-8990
Project Planner: Chris Ramey, (541) 346-5562
Project Manager: George Bleekman, (541) 346-2625
A conceptual design by Jones & Jones Architects for a new Native American Longhouse was completed in Spring 1998. As described in the conceptual design, the longhouse "will express the essential cultural values of welcome, community, and learning for Native American students and peoples. The building will serve as a gathering place... where Native Americans and non-natives can interact and learn from each other."
The new longhouse is located on the site of the former longhouse. The all-wood building has a Great Room for large gatherings, modeled after traditional longhouses of the Kalapuya Indians. Other features include an office, a kitchen, and space for outdoor events.
Status: Completed in January 2005. Grand opening held January 11, 2005. [updated 1/05]
Exterior, Interior Photo, Corridor Photo
Size: approximately 80,000 SF renovation
(4 floors)
Total Project Budget: approximately $4 million (direct construction = 2.5 mil)
Architect: SRG Partnership, Portland (Contact: Hussain Mirza)
Construction Firm: Wildish Building, Eugene
Project Planner: Fred Tepfer
Project Manager: Janet Lobue
The second stage of the Campus Development Project was the renovation of the
former Law School building for university classroom and office use by the College
of Arts and Sciences and other departments, including public interface components
of University Computing.
The renovation of McKenzie Hall (formerly called Grayson Hall) included the
creation of new, state-of-the-art classrooms and offices in former library space,
improvements to existing classrooms, creation of computer labs and seminar rooms,
and other interior remodeling. It also included improvements to accessibility,
entrances, approaches, and the existing courtyard.
The first floor continues to provide space for existing classrooms; University
Computing maintains a documents room and a general university computer lab.
Its software consultants, Help Desk, and computer repair programs are also housed
on this floor. Existing classrooms and lecture halls on the first floor have
been enhanced to support a wider range of teaching styles and methods.
Two of the building entrances have been modified to provide an improved connection
with the university, orienting the building toward the rest of campus. The university
contracted separately with Cameron McCarthy Gilbert & Scheibe, landscape
architects, to design these improvements.
The second floor was remodeled for the department offices of History and Ethnic
Studies. The original moot court has become a film studies classroom; the law
library space has been converted to new flexible media-equipped classrooms,
and the original lecture halls have been improved with better lighting, enhanced
acoustics, and provisions for multimedia presentation.
The third floor has remained faculty offices and includes a faculty lounge,
seminar rooms, GTF offices, a GTF lounge and a classroom. Open spaces have been
made into shared commons.
Three new seminar rooms, a multi-use classroom, and the Social Sciences Instructional
Laboratory were built on the fourth floor, as well as space for the Oregon Survey
Research Laboratory.
Construction was completed in summer 2000 and the building was occupied the
beginning of Fall term.
(ED) MOSHOFSKY
SPORTS CENTER (INTERCOLLEGIATE ATHLETIC FACILITIES IMPROVEMENTS PHASE 1)
(including the Ed Moshofsky Indoor Practice Facility)
Exterior photo, Interior 1, Interior 2, Interior 3
Size: 106,845 SF new construction (1 floor)
Total Project Budget: approximately $13,800,000, private funds (Direct construction
$10,218,000)
Architect: WBGS Architecture, Eugene
Landscape Architect: Cameron McCarthy Gilbert & Scheibe
Construction Firm: Chambers Construction, Eugene
Project Planner: Chris Ramey
Project Manager: Garry Fritz
This project consists of an indoor practice facility which opened in Fall 1998,
a soccer field, and other practice fields for intercollegiate athletics near
Autzen Stadium. It provides the university with indoor practice areas for women's
softball, women's soccer, men's and women's track and golf, and football, along
with outdoor natural grass practice and competition facilities for women's soccer
and outdoor practice facilities for all teams.
(ED) MOSHOFSKY
SPORTS CENTER (INTERCOLLEGIATE ATHLETIC FACILITIES PHASE 2)
Size: approximately
22,600 SF in additions (1 & 2 floors)
Total Project Budget: approximately
$3 million in private gifts
Architect: WBGS Architecture, Eugene
Construction
Firm: Chambers Construction, Eugene
Project Planner: Chris Ramey
Project
Manager: Charlene Lindsay
Phase II consisted of two additions to the
Phase I indoor sports practice facility adjacent to Autzen Stadium (1998). These
additions were part of the original building design and were planned as eventual
enhancements. The two additions contain team medical training and meeting rooms,
classrooms, a commissary, a letterman's lounge, and storage for pre-game functions.
Construction was completed summer 2000.
(JORDAN SCHNITZER) MUSEUM OF ART ADDITIONS AND ALTERATIONS
Museum
of Art web site
Size: approximately 38,000 sf addition and 25,000 gsf renovation (three floors)
Total Project Budget: approximately $12 million - a combination of $6 million
in gifts and grants and $6 million in matching state bonds.
Architect: SRG Architects, Portland, OR (contact: Dennis Cusack), (503) 222-1917
with design consultants Hammond, Beeby, Rupert, and Ainge, Chicago
Construction Firm: Wildish Building Company, Eugene, OR, (541) 485-1700
Project Planner: Chris Ramey, (541) 346-5562
Project Manager: Alex Gordon, (541) 346-5219
Built in 1932, the Museum of Art is Oregon's premier academic art museum. It
receives between 40,000 and 50,000 visitors annually, many arriving from off
campus. The Museum of Art's audiences, collections, programs, and staffing have
long since outgrown the facility. This project will provide an addition for
new galleries, collections storage, a loading dock, new offices, and an auditorium.
It will renovate existing spaces including development of a climate control
system, new electrical systems, asbestos abatement, and ADA improvements. The
creation of an outdoor sculpture courtyard is also part of this project.
Listed on the National Register of Historic Places, the building itself is considered
to be an important part of the Museum's collection of artwork. The project gave
careful and sensitive consideration to the building's campus location, its unique
architectural design, and its historic setting.
Status: Construction began in fall 2002
and was completed in January 2005. The official reopening was January 23, 2005.
[updated 1/05]
Oregon Institute of Marine Biology web site
Size: remodel (second floor)
Total Project Budget: approximately $400,000 in gift funds
Architect: Crow/Clay Architects, Charleston, OR, (541) 269-9388
Construction Firm:
Project Planner: Fred Tepfer, (541) 346-5564
Project Manager: Alex Gordon, (541) 346-5219
Description: This project provided additional office and lab space on the second
floor of the Oregon Institute of Marine Biology's Terwilliger Building. Phase
1 of the project included an addition to the second floor. The exterior shell
of this addition was completed Summer 2001. Phase 2 of the project included
remodeling the unfinished attic space on the second floor, primarily as a lab
and office suite for OIMB's director.
Phase 2 was completed December 2002. [updated 12/02]
SHIRE RETREAT AND STUDY CENTER AT THE JOHN YEON PRESERVE FOR LANDSCAPE STUDIES. FEASIBILITY AND SITING STUDY.
Project Planner: Dorene Steggell (541)
346-5606
Landscape Architect: Walker Macy (503) 228-3122
The Shire occupies 75 acres along the northern bank of the Columbia River Gorge
directly across from Multnomah Falls, approximately 35 miles east of Portland.
It is a carefully designed landscape in a natural context with a sculpted lawn,
a series of meadows, vista points, river bays, and walking paths created by
John Yeon over a 30-year period. The School of Architecture and Allied Arts
plans to create a retreat and study center on the site.
The Shire, with its Retreat and Study Center, will become a national and regional
center for Pacific Northwest landscape and planning studies while being preserved
as an example of landscape design. A study examining the feasibility and siting
options for the development of the Center was completed in January 2005.
See the following website for more information regarding The Shire.
http://landarch.uoregon.edu/index.cfm?mode=facilities&page=shire
Landscape Architect: Cameron McCarthy
Gilbert & Scheibe, Eugene
Project Planner: Dorene Steggell
The signage improvements project at the
Southgate entrance is the last of three priority entrance signage projects proposed
by a review of campus signage several years ago. The other two locations are
Westgate, where signs were installed last fall, and the corner of Franklin Boulevard
and Agate Street, where a large "University of Oregon" sign was installed in
the spring of 1998.
Southgate improvements augment other University Street improvements made in
recent years and serve as both a welcome gateway and means of orientation. The
design contains elements of the existing Westgate (13th and Kincaid) with differences
in materials to reflect the immediate context. The Southgate design replaced
the previous light standards with taller, more massive lighting elements similar
in style to the Westgate design. A bronze, interlocking block 'UO' is embedded
in brick pavement across the entrance.
Construction was completed in Summer 1999.
STUDENT RECREATION [AND FITNESS] CENTER, Phase I - Esslinger Hall Additions & Alterations
Exterior north, Exterior east, All-year field
Implementing The Oregon Experiment with the Recreation Center project
Size: approximately 79,000 SF remodeled/renovated; 49,000 SF addition ( 1 & 2
floors)
Total Project Budget: approximately $17.8 million - $8.8 million student
building fees; $8.7 million student recreation fees; and $.3 million in other
funds.
Architect: TBG Architects & Planners, Eugene, with Cannon Parkin,
Los Angeles
Construction Firm: Hyland Construction, Eugene
Project Planner:
Chris Ramey
Project Manager: Mark Henry
This project consisted of the renovation and expansion of Esslinger Hall and
playing fields. The first phase included an addition which houses new strength
and fitness areas, a three-court gym with a running track, a rock-climbing wall
and a juice bar. The existing locker rooms and laundry areas were remodeled
for locker rooms, administrative offices, the Slocum Lab, athletic training
areas, and storage areas. The first phase also included an exterior, lighted,
artificial field. Other improvements included new accessibility ramps and other
minor repairs. Construction began in March 1998 and was completed in Fall 1999.
The second phase of construction included renovation of the existing gyms, courts and multipurpose rooms as well as the extension the grass field by the Autzen footbridge. Construction was completed in Spring 2000.
STUDENT
RECREATION [AND FITNESS] CENTER, Phase II- Student Indoor Tennis Center
Size: six new courts plus approximately 3,000 SF for the viewing area (Phase I,
1 floor)
Total Project Budget: approximately $2 million of funding for Phase
I of the construction work provided by the Department of Intercollegiate Athletics
($.7 million) and the Recreation and Fitness Center user group ($1.3 million)
Architect: TBG Architects, Eugene
Construction Firm: Hyland Construction,
Springfield
Project Planner: Chris Ramey
Project Manager: Mark Henry
During the planning phase for the Recreation and Fitness Center, discussions
were held among the project user group, representatives of Intercollegiate Athletics,
and PARS staff about how to combine funding for the Recreation Center project
with Athletic Department funding in order to build a new enclosed tennis facility.
The fully enclosed facility for instruction, recreation, and intercollegiate
tennis users replaces four covered courts that were demolished to make way for
the Rec Center. The tennis facility includes a small office and storage area
to be shared by all of the facility's users; restrooms; and a viewing area for
observing matches or instruction. It consists of a prefabricated metal-roofed
structure enclosed with 18-foot walls of articulated concrete masonry units.
The Student Indoor Tennis Center will be built in phases. Phase I, completed
in Fall 2000, consists of a six-court building with associated spaces and a central
viewing area. A later phase will expand the building from six to eight courts
and add a raised viewing platform.
STUDENT RECREATION AND FITNESS CENTER CONCEPT STUDY
PARS worked with the Planning Office and Yost Grube Hall Architects of Portland to analyze the facility's needs and develop a conceptual plan for future additions and alterations. The study was completed spring 2004. It describes two phases of expansion with a total of 111,000 square feet of new construction and 31,700 square feet of renovation. It includes conceptual floor plans, models, and rendered elevations, integrating the existing facility with the new.
Sustainable
Development Plan
Project Planner: Christine Thompson
The university has prepared guidelines for campus sustainable development that have been adopted as part of the Long Range Campus Development Plan. The Campus Planning Committee believes that the University of Oregon should be a world leader in creating and maintaining an environmentally sustainable institution. The University should set examples in the design, construction, and operation of the campus, the management of its fiscal and human resources and the actions of its faculty, staff, and students.
The Sustainable Development Plan was prepared by the Development, Policy, Implementation, and Transportation (DPIT) Subcommittee of the Campus Planning Committee as directed by the university president. It was reviewed and approved by the Campus Planning Committee at a public hearing October 5, 2000. The plan became effective February 15, 2001 when the University received notice that the City of Eugene had determined the "sustainable development" pattern to be consistent with the Area Metro Plan.
Click here for additional information and to view a copy of the Plan.
UNIVERSITY STREET AXIS FRAMEWORK STUDY
Size: exterior
Total Project Budget: approximately $52,750
Landscape Architect: Moore Iacofano
Goltsman, Inc., Eugene
Project Planner: Dorene Steggell
The goal
of this study was to develop a new vision for University Street and common open
spaces that intersect the heart of the campus. A User Group, Focus Group, and
campus-wide comment session offered opportunities for the campus community to
participate.
The study was completed in Spring 2001.
Construction Photo 1, Construction Photo 2
Size approximately
2,600 SF addition (one story)
Total Project Budget: approximately $600,000,
a combination of F-bonds ($340,000) and private gifts
Architect: De Norval
Unthank Architect, Eugene
Construction Firm: Morris Kielty, Eugene
Project
Planner: Dorene Steggell
Project Manager: Janet Lobue
The existing Vivian Olum Child Development Center was designed to be developed in two phases. The architect for the original design, De Norval Unthank, worked with the user group to design Phase II, an addition (the Lois Schafpf Reed Wing) to the existing center. The addition allows the center to consolidate its program into one building, and to provide services to 13 additional children and their families. The program and size are similar to the originally planned Phase II. The configuration on the site was slightly modified to allow for more contiguous space to be left to the north of the building. Site preparation work began in Fall 2000 with demolition of one of the old, existing structures along the alley to the west of the existing center.
The schematic design phase was completed in Summer 1999. Construction was completed in Fall 2000.
Project Planner: Fred Tepfer
The 15th Avenue improvements, built in the summer of 2004, increased parking significantly in the area of the Living Learning Center and also enhanced that part of campus with new trees, shrubs, irrigation, raised pedestrian crossings, and other features.