Projects completed in 1997-2005:

(listed in alphabetical order)


ALLEN HALL RENOVATION

Rapid growth of the student body and faculty in the School of Journalism and Communication, along with escalating needs for specialized classrooms and resource facilities, has triggered the need to renovate Allen Hall. Planning for the complete renovation of Allen Hall was based on a November 13, 1995 master plan study by Boucher Mouchka Larson Architects (BML). Phases I and II were completed in earlier years. Total project budget: $3.5 million.

 


ALLEN HALL RENOVATION PHASE III - RESOURCE ROOM

Interior Photo, Exterior Photo

Size: approximately 1,400 sf remodeling (1 floor)
Total Project Budget: approximately $373,000 private funds (Direct construction $282,000)
Architect: Boucher Mouchka Larson Architects (BML), Portland
Construction Firm: Morris P. Kielty, Eugene
Project Manager: Alex Gordon
Project Planner: Chris Ramey

This phase created a Resource Room (Willis S. Dunaway Journalism Resource Room), which provides new space designed for study, meetings, and student research. As the School's curriculum increasingly becomes project-oriented with strong emphasis on team and individual projects, space is needed for student meetings and team conferences, and students need greater access to computers and computer networks. The Resource Room meets all of these needs. In addition, a schematic design for a new entry was completed. Construction was completed in Spring 1999.


ALLEN HALL RENOVATION PHASE IV

Exterior Photo 1, Interior Photo

Size: approximately 1,100 SF addition (1 & 2 floors)
Total Project Budget: approximately $850,000 private funds
Architect: Boucher Mouchka Larson Architects (BML), Portland
Landscape Architect: Cameron McCarthy Gilbert, Eugene
Construction Firm: Morris P. Kielty, Eugene
Project Planner: Chris Ramey
Project Manager: Alex Gordon

This phase included the creation of a new 1,100 SF building entry which efficiently connects the two portions of the lower floors with each other and with the rest of the building. Additionally, because the ground floor of the building is below grade, an entry plaza was designed to adjust from the surrounding grade to the entrance level through a series of gradual transitions to the existing contours.

Phase IV included a conference room devoted to alumni recognition and the Dean's Complex, consisting of a two-room Dean's suite with private office, staff office and support area. Construction began in Summer 1999 and was completed in April 2000.


ALLEN HALL RENOVATION, Phase V

Size: approximately 21,700 gsf remodeled space
Total Project Budget: approximately $2,000,000 in mostly gifts, but also including $561,800 in G-bonds.
Architect: Boucher Mouchka Larson Architects (BML), Portland, OR, (503) 223-4886
Construction Firm: DPR Construction, Eugene, OR, (541) 341-1329
Project Planner: Chris Ramey, (541) 346-5562
Project Manager: Alex Gordon, (541) 346-5219

Description: This phase made improvements to the second and third floors including conversion of the resource room to an electronic classroom and conversion of the old Dean's office to faculty offices.

Status: Construction completed Fall 2001.


AUTZEN STADIUM

Location: Autzen Stadium
Size: approximately 12,000 new seats and renovation.
Total Project Budget: $89.7 million ($72 million direct construction)
Architect: Ellerbe Becket, Kansas City, MO (816) 561-4443
Construction Firm: Hunt/Wildish, Eugene (541) 485-1700
Project Planner: Chris Ramey, (541) 346-5562
Project Manager: Charlene Lindsay, (541) 346-5276

Description: The stadium expansion design addressed the need to expand seating capacity and the need to improve circulation, accessibility, restrooms, concessions, and press facilities. It took into consideration the original design by Skidmore, Owings, and Merrill, which displays axial geometry, symmetrical massing, easily understood circulation, and the use of the berm as a podium for the stadium. The phased expansion and renovation project added 12,000 new seats, 3,000 of which are located in a new covered "club section," along with 32 new skyboxes, a three-story luxury suite, and improved concession stands. These improvements are expected to produce more revenue, thus helping the athletic department to become completely self-funding. The total stadium capacity increased from 41,700 to 53,800 seats.

The site master plan addressed the need for improved circulation, parking, transit capacity, accessibility, and pre-game activity amenities (including new restroom facilities).

The schematic design was completed in winter 2000. Phase 1 of the project, including landscaping of the north berm, was completed in 2000. Phase 2, including new artificial turf; the new bus transit station; new water, sewer, and electrical facilities; new ticket booths; and a decorative fence around the stadium, was completed in summer 2001. Phase 3, including the addition of 12,000 new seats, improved restrooms, concessions, and walkways, were completed before the 2002 football season. Phase 4, including the addition of new sky suites and pressbox, was finished by the 2003 season.

Status: Completed summer 2003.


CAMPUS DEVELOPMENT PROJECT

Faced with the twin challenges of increased numbers of students and outmoded classroom facilities, the university embarked on a three-phase project to expand and modernize core academic space on the campus. Stage One (see William W. Knight Law School) of the project relocated the Law School to a new building on land available at the eastern edge of the campus periphery (completed), freeing up the central campus space of the previous Law building (McKenzie Hall) for general educational uses. The renovation of McKenzie Hall, Stage Two (see McKenzie Hall Renovation), is also completed. Stage three of the project is the Lillis Hall/Gilbert Hall Additions and Alterations Project. Lilles Hall was completed in winter 2004


CAMPUS DIAGNOSIS STUDIES

Project Planner: Christine Thompson, (541) 346-5572

The purpose of diagnosis studies is to record the existing conditions of the campus as they relate to the university's Long Range Campus Development Plan's policies and patterns. These studies aid in decision making for potential development of the area, as well as help identify the need for future amendments to the Long Range Campus Development Plan.

For more information click here.

Status: Completed.


CAMPUS PLAN UPDATE

Project Planners: Chris Ramey, (541) 346-5562 and Christine Thompson, (541) 346-5572

The University of Oregon began the process of updating its Campus Plan (previously known as the 1991 Long Range Campus Development Plan) in the summer of 2004.

The Campus Plan describes the guiding principles (or patterns) and policies that define the type and extent of future campus development. The 1991 LRCDP was written nearly fifteen years ago. It has effectively guided the university through an active period of development and improvements resulting in a noticeably enhanced campus environment. Change happens incrementally, making an overall guiding plan essential. The plan's basic precepts remain very effective. Nonetheless, it is important to revisit portions of the LRCDP to evaluate potential improvements to the planning process and to fix outdated information. These efforts will ensure that the LRCDP will serve the campus for the next ten years.

A draft updated Campus Plan was completed and reviewed by a wide body of individuals and groups during a three-month time period beginning January 11, 2005 and ending with the CPC April 12, 2005 public hearing. The Campus Planning Committee reviewed the comments and suggestions gathered during this review period prior and took action May 24, 2005. The CPC's recommendation for approval was supported by university administration.

Click here to see the updated Campus Plan.

Status: Completed


CAMPUS OUTDOOR LIGHTING PLAN

Project Planner: Christine Thompson, (541) 346-5572

Description: The purpose of the Campus Outdoor Lighting Plan is to interpret and enhance the existing Long Range Campus Development Plan (LRCDP) outdoor lighting policies creating a Level 3 Plan. The plan defines lighting parameters for entrances, pedestrian walkways, and parking lots on campus. It also describes review requirements and defines the campus standard light fixture design.

Outdoor lighting on campus has received a great deal of attention over the years. This plan is designed to address the key issues and concerns surrounding the subject. Establishing a plan (in particular prioritizing outdoor lighting walkways) will also allow the CPC to review outdoor lighting improvements in a comprehensive manner, thus eliminating the need for individual lamp location reviews.

Status: Completed winter 2004.


CAMPUS TREE PLAN

Project Planner: Christine Thompson, (541) 346-5572

The Campus Tree Plan, created by the Campus Planning Committee, will guide future care for the trees on campus to ensure that they remain a vital component of the campus environment. The university has had in place other policies (Long Range Campus Development Plan) which address tree management, but the policies lacked specificity and were not comprehensive. The new Campus Tree Plan ensures that all development, repair, maintenance and operations of the University of Oregon campus incorporate tree management principles addressing tree protection, tree replacement, landscape design, and environmental sustainability.

The Campus Tree Plan became available in October, 2001.


EAST CAMPUS (MOSS STREET) CHILDREN'S CENTER

Location: East Campus
Size: 13,500 sf
Total Project Budget: approximately $2.8 million
Architect: Mahlum Architects, Portland, OR, (503) 224-4032
Construction Firm: Ordell, Springfield, OR, (541) 747-8734
Project Planner: Dorene Steggell, (541) 346-5606 Project Manager: George Bleekman, (541) 346-2625

This 2.8 million dollar 13,500-square-foot project replaced the former Child Care and Development Center facilities occupying houses in East Campus and the EMU. The new Center serves approximately 120 children, infants through school-aged, of university students, faculty, and staff. The Center has many sustainable aspects, including daylighting, and ground-source heat pumps.

Status: The grand opening was held in May 2004. [updated 1/05]


EAST CAMPUS DEVELOPMENT POLICY UPDATE

Project Planners: Chris Ramey, (541) 346-5562 and Christine Thompson, (541) 346-5572

The university, with input from neighbors and campus community members, created a new policy for East Campus development. The policy's goal is to provide for the expansion of the institution, based on its needs, without diminishing the quality of the surrounding neighborhood. It describes the type and extent of future development in the East Campus Area. The policy addresses the following key elements: university mission, graceful edges, campus-like character, traffic, parking, maintenance, and communication.

Click here for more information about the project.

Status: The project was completed Fall 2004.


EASTGATE

Sketches: Goal 1, Goal 2, Goal 3, Goal 4

Landscape Architect: Cameron McCarthy Gilbert & Scheibe, Eugene, along with the consulting firm of Moore, Iacofano, and Goltsman (MIG), Eugene.
Project Planner: Dorene Steggell

This project is one of a series of projects that looks at ways to improve campus gateways. Well-developed entrances to the campus increase coherency and create a sense of the campus as a definable space. The Eastgate project covers the area between Oregon Hall and the University Health and Counseling Center and its surroundings. This area is particularly important because it is the first point of arrival for prospective students, staff, faculty, and campus visitors. It also is a key component of the university's vehicular circulation system.

A steering committee was established and worked with the landscape architecture firm on the Feasibility Study. A workshop was held February 5, 1999 to gain input from a broader focus group. The results of this meeting were presented at a campus-wide presentation.

The Feasibility Study report, completed August 1999, identified four conceptual goals: (1) sense of arrival, (2) traffic control, (3) reflection of the Oregon landscape, and (4) front doors to buildings.


(COLLEGE OF) EDUCATION CONCEPTUAL DESIGN

Size: approximately 94,000 gsf new construction and 17,000 gsf alterations
Total Project Budget: approximately $40 million
Architect: Zimmer Gunsul Frasca Partnership, Portland, OR, (503) 224-3860
Project Planner: Chris Ramey, (541) 346-5562
Project Manager:

The College of Education is growing in response to a statewide need for effective teachers and school administrators and to substantial growth in research and service funding. The investment in physical facilities is essential to sustaining faculty productivity, program quality, and impact of faculty research and outreach services. Faculty, staff and students have been assigned to crowded, substandard, and/or remote structures. The recommended addition of 94,174 gsf of new space and renovation of 17,200 gsf of existing space will remedy current, serious space and functional problems and provide a modest increment for growth, if used prudently.

Status: The conceptual design is completed and fundraising is under way. [updated 12/03]


EMU MASTER PLAN

Size: approximately 213,000 gsf (three floors)
Total Project Budget: approximately $200,000
Architect: MHTN Architects, Salt Lake City, UT, (801) 595-6700
Project Planner: Chris Ramey, (541) 346-5562

Since 1950, the Erb Memorial Union (EMU) has been the gathering place for campus activities at the University of Oregon. It houses more than 150 student groups and provides lounges, art galleries, a variety of food venues, a pool hall and arcade, a number of services, group meeting rooms, and a staff of program consultants to assist the student groups. The fifty-year-old building has undergone at least three additions or renovations during its lifetime.

This master plan contains a conceptual program for accommodating the EMU's space needs for the next 20 years, and a basic diagrammatic vision for how the needed space can be accommodated including identification of discrete construction phases which could be implemented over a number of years.

Status: The master plan is completed. [updated 12/03]


ERB MEMORIAL UNION FOOD SERVICE & REC CENTER IMPROVEMENTS

The Fish Bowl Photo, The Buzz Photo, Rec Center Photo

Size: approximately 3,000 addition; 49,000 SF remodeled/renovated; (2 floors)
Total Project Budget: approximately $4,520,000 (Direct construction $3,224,000)
Architect: McBride/Seder Architects, Portland
Construction Firm: Wildish Building Co., Eugene
Project Planner: Fred Tepfer
Project Manager: Garry Fritz

This project remodeled the south and west areas of the basement and ground floors of the Erb Memorial Union building. Completed in the summer of 1998, it revised and improved circulation and visibility in the Fishbowl and south dining room areas, restoring many circulation patterns that were disrupted by the previous building addition and remodel. At the basement level, the project added approximately 3,000 square feet, revising and clarifying the corridors and circulation, and remodeling the Recreation Center and Quick Copy. The Convenience Store also is now located in the remodeled space. The new north addition, next to the current breezeway and with an entrance clearly visible from 13th and University, contains a coffee house. Source of funds: 85% building fees; 15% state system utilities funds.


ERB MEMORIAL UNION AMPHITHEATER

Photo

Size: courtyard
Total Project Budget: approximately $415,000 from incidental fees (Direct construction $348,000)
Landscape Architect: Cameron McCarthy Gilbert & Scheibe, Eugene
Construction Firm:
Project Planner: Fred Tepfer
Project Manager: Garry Fritz

This project, completed in the summer of 1998, was initiated on behalf of the ASUO by the 1996-97 ASUO President to commemorate the organization's 100-year anniversary. The project repaired and improved the portion of the campus located between the EMU and the intersection of 13th Avenue and University Street (approximately 24,000 SF). The landscape architect worked with a user group of students, faculty, and staff. The project removed paving and some of the existing trees and constructed a plaza near the intersection, one more suitable for large group gatherings than the previous series of smaller spaces. It includes a raised "stage," and all areas are accessible by gently sloping sidewalks that are more manageable for people with disabilities. The project creates a more open view of the EMU and also includes a clear path up to the main entrance of the building. This project's support was due largely to enormous efforts on the part of the ASUO, the user group, the consultant, and the general contractor working in very complementary and productive ways. Source of funds: student incidental fees.


ERB MEMORIAL UNION ELEVATOR

Photo

Size: elevator addition (1 floor)
Total Project Budget: approximately $555,000 - Student building fee financing (Direct construction $351,000)
Architect: Robertson/Sherwood Architects, Eugene
Construction Firm: 2G Construction
Project Planner: Chris Ramey
Project Manager: Alex Gordon

This project, comprised of an elevator in the Erb Memorial Union building, provides access to the International Student Lounge, the Oregon Daily Emerald offices, and the Adell McMillan Art Gallery. Construction was completed in Winter 2000.

 


fMRI FACILITY/STRAUB HALL ADDITIONS AND ALTERATIONS

Size: approximately 1,000 gsf addition and 2,000 gsf remodel (one story)
Total Project Budget: $4,032,400 (includes $1,166,000 in G-bonds) for Straub Hall alterations plus additional grant funds from fMRI grant application.
Architect: L. A. Kersh Architecture, Eugene, (541) 334-6408
Construction Firm: Hyland Construction, Springfield, OR, (541) 725-8081
Project Planner: Dorene Steggell, (541) 346-5606
Project Manager: George Bleekman, (541) 346-2625

Description: The Straub Hall Additions and Alterations Project, approved by the 1999 legislature, provides additional space for the Psychology Department. The project includes a small addition which houses the new fMRI facility, plus a remodel of adjacent existing space on the first floor of Straub Hall. The new Lewis Neuroimaging Center permits imaging of brain function and brain tissue that will allow scientists to better correlate the brain's anatomy with human thought and behavior.

 


HAYWARD PLAZA

Click here for Rendering of Hayward Plaza

Click here for Rendering of Hayward Plaza Entry

Location: Corner of Agate and 15th Streets
Total Project Budget: $950,000
Landscape Architect: Cameron McCarthy Gilbert Scheibe (541) 485-7385
Construction Firm: Brown Construction Company
Project Planner: Chris Ramey (541) 346-5562
Project Manager: Charlene Lindsay (541) 346-5276

The Hayward Plaza Project brings together two long-standing needs at this facility: creating a welcoming "front door" for the facility and providing an opportunity to recognize the great heritage of Hayward Field and the University of Oregon Track and Field programs.

This project will create a welcoming arrival point for Hayward Field as well as enhancing a significant campus entrance. The plaza project will incorporate displays telling the story of Hayward Field and our Track & Field programs. The design provides for access to these display areas for casual, weekday visitors as well as those attending events at the facility.

Status: Completed 2005.

 


HEART OF CAMPUS

Total Project Budget: approximately $690,000
Landscape Architect: Cameron McCarthy Gilbert Scheibe, (541) 485-7385
Construction Firm: Wildish Companies, (541) 485-1700/UO Landscape Students
Project Planner: Dorene Steggell, (541) 346-5606
Project Manager: Janet Lobue, (541) 346-5259

Construction is complete on the new Heart of Campus, which consists of replacement of the existing kiosk and the creation of a pedestrian-friendly plaza at the intersection of 13th Avenue and University Street. The project was funded by the sale of engraved bricks to commemorate the 125th anniversary of the University, and by the Department of Public Safety. The School of Architecture and Allied Arts and Facilities Services made significant in-kind contributions. The kiosk and surrounding areas were designed and constructed by UO Landscape students working with Professor Stan Jones. The street improvements were designed by Cameron McCarthy Gilbert Schiebe.

Status: Completed in fall 2004.


(LEE) KELLY SCULPTURE

Total Project Budget: approximately $25,000
Engineering Consultant: MR Richards Engineering, Inc., Eugene
Project Planner: Dorene Steggell, (541) 346-5606

This project addressed the siting and installation of a large, donated sculpture titled Akbar's Garden by prominent Northwest artist Lee Kelly. The Straub Hall Quadrangle was selected by the artist and the donor as an appropriate site for the sculpture, which was installed there in June 2002.


(WILLIAM W.) KNIGHT LAW CENTER

Exterior NW photo , Exterior West , Interior 1, Interior 2, Interior 3
Link to Law Center's Blueprint tour and Factsheets

Size: 138,000 SF new construction (4 floors)
Total Project Budget: approx. $25 million - state bonds ($10.3 million) and private gifts ($14.7 million). Direct construction $21,691,000
Architect: Yost Grube Hall, Portland
Construction Firm: Hoffman Construction Co., Portland
Project Planner: Chris Ramey
Project Manager: Janet Lobue

The new Knight Law Center at the corner of 15th Avenue and Agate Street was the first stage of the Campus Development Project. The Law Center houses the Law library and has boosted overall Law School space by almost 50% to accommodate 565 instruction stations, 41 faculty offices, and several administrative areas. The new center better fits the way law is taught today, with more small classrooms and seminar rooms, a student lounge, a moot courtroom, areas for groups to meet, and access to the latest technology. It was designed by Portland architectural firm Yost Grube Hall. The Law School moved in Summer 1999 when final construction was completed.


LILLIS HALL/ GILBERT HALL ADDITIONS AND ALTERATIONS, PHASE THREE

Size: net additional square footage is approximately 90,000 sf (four floors) plus replacement of 45,000 gsf (1952 Gilbert bridge) and remodeling of 37,000 gsf (east and west buildings, three floors).
Total Project Budget: approximately $38.9 million - state "G" bonds ($3.45 million), matching private gifts ($3.45 million), state "F" bonds ($100,000), and additional gift funds from Lundquist College donors.
Architect: SRG Partnership, Portland, OR (contact: Hussain Mirza), (503) 222-1917
Construction Firm: Lease Crutcher Lewis, Portland, OR (CM/GC), (503) 223-0500
Project Planner: Fred Tepfer, (541) 346-5564
Project Manager: Janet Lobue, (541) 346-5259

The Lillis Hall/Gilbert Hall Additions and Alterations Project represents the final stage of the Campus Development Project. It relieved some of the need for general classroom space on campus.

The newly configured Lillis Business Complex, which houses the Lundquist College of Business in four separate, linked structures, connects the UO's west entrance to the Memorial Quadrangle. Its prominent location and Gilbert Hall's historic role as the first element of what became the Memorial Quadrangle (listed on the National Register of Historic Places) give it pivotal importance both on the campus map and in campus history.

This project is the first comprehensive addition and alteration project for Gilbert Hall in nearly 50 years. Since the center bridge connector (commonly referred to as the "Commonwealth Bridge") was opened in 1952, this building complex has been expanded and remodeled, but always without a comprehensive study of the long-range needs of the College of Business.

The project created a unified facility that fosters interaction among students and faculty and supports teaching and learning in the classroom, in self-directed teams, and in internships. It gives the College state-of-the-art teaching and support facilities, a new look and new front door onto the campus that it and the rest of the university can be proud of.

Structural - Degenkolb Engineers; Mechanical/Electrical/Civil - Balzhiser & Hubbard Engineers; Landscape Architect - Cameron, McCarthy, Gilbert & Scheibe; Life Safety Ð Creighton Engineering.

Status: Construction of Lillis Hall was completed in late fall 2003. Planning will begin in 2004 for renovation of the historic Gilbert (east) and Peterson (west) wings. [updated 3/05]


MANY NATIONS LONGHOUSE

Longhouse web site

Size: 3,500 square feet new construction (one story)
Total Project Budget: approximately $1.2 million (student building fees and gifts)
Architect: Jones & Jones Architects and Landscape Architects, Seattle, WA, (206) 624-5702
Construction Firm: Preferred Construction Inc., Springfield, OR (541) 726-8990
Project Planner: Chris Ramey, (541) 346-5562
Project Manager: George Bleekman, (541) 346-2625

A conceptual design by Jones & Jones Architects for a new Native American Longhouse was completed in Spring 1998. As described in the conceptual design, the longhouse "will express the essential cultural values of welcome, community, and learning for Native American students and peoples. The building will serve as a gathering place... where Native Americans and non-natives can interact and learn from each other."

The new longhouse is located on the site of the former longhouse. The all-wood building has a Great Room for large gatherings, modeled after traditional longhouses of the Kalapuya Indians. Other features include an office, a kitchen, and space for outdoor events.

Status: Completed in January 2005. Grand opening held January 11, 2005. [updated 1/05]


MCKENZIE HALL RENOVATION

Exterior, Interior Photo, Corridor Photo

Size: approximately 80,000 SF renovation (4 floors)
Total Project Budget: approximately $4 million (direct construction = 2.5 mil)
Architect: SRG Partnership, Portland (Contact: Hussain Mirza)
Construction Firm: Wildish Building, Eugene
Project Planner: Fred Tepfer
Project Manager: Janet Lobue

The second stage of the Campus Development Project was the renovation of the former Law School building for university classroom and office use by the College of Arts and Sciences and other departments, including public interface components of University Computing.

The renovation of McKenzie Hall (formerly called Grayson Hall) included the creation of new, state-of-the-art classrooms and offices in former library space, improvements to existing classrooms, creation of computer labs and seminar rooms, and other interior remodeling. It also included improvements to accessibility, entrances, approaches, and the existing courtyard.

The first floor continues to provide space for existing classrooms; University Computing maintains a documents room and a general university computer lab. Its software consultants, Help Desk, and computer repair programs are also housed on this floor. Existing classrooms and lecture halls on the first floor have been enhanced to support a wider range of teaching styles and methods.

Two of the building entrances have been modified to provide an improved connection with the university, orienting the building toward the rest of campus. The university contracted separately with Cameron McCarthy Gilbert & Scheibe, landscape architects, to design these improvements.

The second floor was remodeled for the department offices of History and Ethnic Studies. The original moot court has become a film studies classroom; the law library space has been converted to new flexible media-equipped classrooms, and the original lecture halls have been improved with better lighting, enhanced acoustics, and provisions for multimedia presentation.

The third floor has remained faculty offices and includes a faculty lounge, seminar rooms, GTF offices, a GTF lounge and a classroom. Open spaces have been made into shared commons.

Three new seminar rooms, a multi-use classroom, and the Social Sciences Instructional Laboratory were built on the fourth floor, as well as space for the Oregon Survey Research Laboratory.

Construction was completed in summer 2000 and the building was occupied the beginning of Fall term.

 


(ED) MOSHOFSKY SPORTS CENTER (INTERCOLLEGIATE ATHLETIC FACILITIES IMPROVEMENTS PHASE 1) (including the Ed Moshofsky Indoor Practice Facility)

Exterior photo, Interior 1, Interior 2, Interior 3

Size: 106,845 SF new construction (1 floor)
Total Project Budget: approximately $13,800,000, private funds (Direct construction $10,218,000)
Architect: WBGS Architecture, Eugene
Landscape Architect: Cameron McCarthy Gilbert & Scheibe
Construction Firm: Chambers Construction, Eugene
Project Planner: Chris Ramey
Project Manager: Garry Fritz

This project consists of an indoor practice facility which opened in Fall 1998, a soccer field, and other practice fields for intercollegiate athletics near Autzen Stadium. It provides the university with indoor practice areas for women's softball, women's soccer, men's and women's track and golf, and football, along with outdoor natural grass practice and competition facilities for women's soccer and outdoor practice facilities for all teams.


(ED) MOSHOFSKY SPORTS CENTER (INTERCOLLEGIATE ATHLETIC FACILITIES PHASE 2)

Exterior, Interior, Duck Shop

Size: approximately 22,600 SF in additions (1 & 2 floors)
Total Project Budget: approximately $3 million in private gifts
Architect: WBGS Architecture, Eugene
Construction Firm: Chambers Construction, Eugene
Project Planner: Chris Ramey
Project Manager: Charlene Lindsay

Phase II consisted of two additions to the Phase I indoor sports practice facility adjacent to Autzen Stadium (1998). These additions were part of the original building design and were planned as eventual enhancements. The two additions contain team medical training and meeting rooms, classrooms, a commissary, a letterman's lounge, and storage for pre-game functions.

Construction was completed summer 2000.


(JORDAN SCHNITZER) MUSEUM OF ART ADDITIONS AND ALTERATIONS

Museum of Art web site

Size: approximately 38,000 sf addition and 25,000 gsf renovation (three floors)
Total Project Budget: approximately $12 million - a combination of $6 million in gifts and grants and $6 million in matching state bonds.
Architect: SRG Architects, Portland, OR (contact: Dennis Cusack), (503) 222-1917 with design consultants Hammond, Beeby, Rupert, and Ainge, Chicago
Construction Firm: Wildish Building Company, Eugene, OR, (541) 485-1700
Project Planner: Chris Ramey, (541) 346-5562
Project Manager: Alex Gordon, (541) 346-5219

Built in 1932, the Museum of Art is Oregon's premier academic art museum. It receives between 40,000 and 50,000 visitors annually, many arriving from off campus. The Museum of Art's audiences, collections, programs, and staffing have long since outgrown the facility. This project will provide an addition for new galleries, collections storage, a loading dock, new offices, and an auditorium. It will renovate existing spaces including development of a climate control system, new electrical systems, asbestos abatement, and ADA improvements. The creation of an outdoor sculpture courtyard is also part of this project.

Listed on the National Register of Historic Places, the building itself is considered to be an important part of the Museum's collection of artwork. The project gave careful and sensitive consideration to the building's campus location, its unique architectural design, and its historic setting.

Status: Construction began in fall 2002 and was completed in January 2005. The official reopening was January 23, 2005. [updated 1/05]


OIMB TERWILLIGER LAB REMODEL

Oregon Institute of Marine Biology web site

Size: remodel (second floor)
Total Project Budget: approximately $400,000 in gift funds
Architect: Crow/Clay Architects, Charleston, OR, (541) 269-9388
Construction Firm:
Project Planner: Fred Tepfer, (541) 346-5564
Project Manager: Alex Gordon, (541) 346-5219

Description: This project provided additional office and lab space on the second floor of the Oregon Institute of Marine Biology's Terwilliger Building. Phase 1 of the project included an addition to the second floor. The exterior shell of this addition was completed Summer 2001. Phase 2 of the project included remodeling the unfinished attic space on the second floor, primarily as a lab and office suite for OIMB's director.
Phase 2 was completed December 2002. [updated 12/02]


SHIRE RETREAT AND STUDY CENTER AT THE JOHN YEON PRESERVE FOR LANDSCAPE STUDIES. FEASIBILITY AND SITING STUDY.

Project Planner: Dorene Steggell (541) 346-5606
Landscape Architect: Walker Macy (503) 228-3122

The Shire occupies 75 acres along the northern bank of the Columbia River Gorge directly across from Multnomah Falls, approximately 35 miles east of Portland. It is a carefully designed landscape in a natural context with a sculpted lawn, a series of meadows, vista points, river bays, and walking paths created by John Yeon over a 30-year period. The School of Architecture and Allied Arts plans to create a retreat and study center on the site.

The Shire, with its Retreat and Study Center, will become a national and regional center for Pacific Northwest landscape and planning studies while being preserved as an example of landscape design. A study examining the feasibility and siting options for the development of the Center was completed in January 2005.

See the following website for more information regarding The Shire.
http://landarch.uoregon.edu/index.cfm?mode=facilities&page=shire


SOUTHGATE

Photo 1, Photo 2

Landscape Architect: Cameron McCarthy Gilbert & Scheibe, Eugene
Project Planner: Dorene Steggell

The signage improvements project at the Southgate entrance is the last of three priority entrance signage projects proposed by a review of campus signage several years ago. The other two locations are Westgate, where signs were installed last fall, and the corner of Franklin Boulevard and Agate Street, where a large "University of Oregon" sign was installed in the spring of 1998.

Southgate improvements augment other University Street improvements made in recent years and serve as both a welcome gateway and means of orientation. The design contains elements of the existing Westgate (13th and Kincaid) with differences in materials to reflect the immediate context. The Southgate design replaced the previous light standards with taller, more massive lighting elements similar in style to the Westgate design. A bronze, interlocking block 'UO' is embedded in brick pavement across the entrance.

Construction was completed in Summer 1999.


STUDENT RECREATION [AND FITNESS] CENTER, Phase I - Esslinger Hall Additions & Alterations

Exterior north, Exterior east, All-year field

Implementing The Oregon Experiment with the Recreation Center project

Size: approximately 79,000 SF remodeled/renovated; 49,000 SF addition ( 1 & 2 floors)
Total Project Budget: approximately $17.8 million - $8.8 million student building fees; $8.7 million student recreation fees; and $.3 million in other funds.
Architect: TBG Architects & Planners, Eugene, with Cannon Parkin, Los Angeles
Construction Firm: Hyland Construction, Eugene
Project Planner: Chris Ramey
Project Manager: Mark Henry

This project consisted of the renovation and expansion of Esslinger Hall and playing fields. The first phase included an addition which houses new strength and fitness areas, a three-court gym with a running track, a rock-climbing wall and a juice bar. The existing locker rooms and laundry areas were remodeled for locker rooms, administrative offices, the Slocum Lab, athletic training areas, and storage areas. The first phase also included an exterior, lighted, artificial field. Other improvements included new accessibility ramps and other minor repairs. Construction began in March 1998 and was completed in Fall 1999.

The second phase of construction included renovation of the existing gyms, courts and multipurpose rooms as well as the extension the grass field by the Autzen footbridge. Construction was completed in Spring 2000.


STUDENT RECREATION [AND FITNESS] CENTER, Phase II- Student Indoor Tennis Center

Exterior Photo

Size: six new courts plus approximately 3,000 SF for the viewing area (Phase I, 1 floor)
Total Project Budget: approximately $2 million of funding for Phase I of the construction work provided by the Department of Intercollegiate Athletics ($.7 million) and the Recreation and Fitness Center user group ($1.3 million)
Architect: TBG Architects, Eugene
Construction Firm: Hyland Construction, Springfield
Project Planner: Chris Ramey
Project Manager: Mark Henry

During the planning phase for the Recreation and Fitness Center, discussions were held among the project user group, representatives of Intercollegiate Athletics, and PARS staff about how to combine funding for the Recreation Center project with Athletic Department funding in order to build a new enclosed tennis facility.

The fully enclosed facility for instruction, recreation, and intercollegiate tennis users replaces four covered courts that were demolished to make way for the Rec Center. The tennis facility includes a small office and storage area to be shared by all of the facility's users; restrooms; and a viewing area for observing matches or instruction. It consists of a prefabricated metal-roofed structure enclosed with 18-foot walls of articulated concrete masonry units.

The Student Indoor Tennis Center will be built in phases. Phase I, completed in Fall 2000, consists of a six-court building with associated spaces and a central viewing area. A later phase will expand the building from six to eight courts and add a raised viewing platform.


STUDENT RECREATION AND FITNESS CENTER CONCEPT STUDY

PARS worked with the Planning Office and Yost Grube Hall Architects of Portland to analyze the facility's needs and develop a conceptual plan for future additions and alterations. The study was completed spring 2004. It describes two phases of expansion with a total of 111,000 square feet of new construction and 31,700 square feet of renovation. It includes conceptual floor plans, models, and rendered elevations, integrating the existing facility with the new.


SUSTAINABLE DEVELOPMENT PLAN

Sustainable Development Plan

Project Planner: Christine Thompson

The university has prepared guidelines for campus sustainable development that have been adopted as part of the Long Range Campus Development Plan. The Campus Planning Committee believes that the University of Oregon should be a world leader in creating and maintaining an environmentally sustainable institution. The University should set examples in the design, construction, and operation of the campus, the management of its fiscal and human resources and the actions of its faculty, staff, and students.

The Sustainable Development Plan was prepared by the Development, Policy, Implementation, and Transportation (DPIT) Subcommittee of the Campus Planning Committee as directed by the university president. It was reviewed and approved by the Campus Planning Committee at a public hearing October 5, 2000. The plan became effective February 15, 2001 when the University received notice that the City of Eugene had determined the "sustainable development" pattern to be consistent with the Area Metro Plan.

Click here for additional information and to view a copy of the Plan.


UNIVERSITY STREET AXIS FRAMEWORK STUDY

University Street Concept

Size: exterior
Total Project Budget: approximately $52,750
Landscape Architect: Moore Iacofano Goltsman, Inc., Eugene
Project Planner: Dorene Steggell

The goal of this study was to develop a new vision for University Street and common open spaces that intersect the heart of the campus. A User Group, Focus Group, and campus-wide comment session offered opportunities for the campus community to participate.

The study was completed in Spring 2001.


VIVIAN OLUM CHILD DEVELOPMENT CENTER

Construction Photo 1, Construction Photo 2

Size approximately 2,600 SF addition (one story)
Total Project Budget: approximately $600,000, a combination of F-bonds ($340,000) and private gifts
Architect: De Norval Unthank Architect, Eugene
Construction Firm: Morris Kielty, Eugene
Project Planner: Dorene Steggell
Project Manager: Janet Lobue

The existing Vivian Olum Child Development Center was designed to be developed in two phases. The architect for the original design, De Norval Unthank, worked with the user group to design Phase II, an addition (the Lois Schafpf Reed Wing) to the existing center. The addition allows the center to consolidate its program into one building, and to provide services to 13 additional children and their families. The program and size are similar to the originally planned Phase II. The configuration on the site was slightly modified to allow for more contiguous space to be left to the north of the building. Site preparation work began in Fall 2000 with demolition of one of the old, existing structures along the alley to the west of the existing center.

The schematic design phase was completed in Summer 1999. Construction was completed in Fall 2000.


15TH AVENUE IMPROVEMENTS

Project Planner: Fred Tepfer

The 15th Avenue improvements, built in the summer of 2004, increased parking significantly in the area of the Living Learning Center and also enhanced that part of campus with new trees, shrubs, irrigation, raised pedestrian crossings, and other features.

 


For additional information, contact the University Planning Office at (541)346-5562