Current Status  

Programming and Schematic Design

 
Project Timeline  

Schematic Design complete March 1, 2012
Design Development complete August 1, 2012
Construction Documents complete February 1, 2013

 
Project Summary  

Location:Expansion site is the existing covered tennis court area east and south of the existing recreation center.

Size: approximately 100,000 sf of new building area and a yet to be determined amount of renovated area

Legislative Authorization:

Expenditure Limitation:

Funding:$50 million total projected project cost subject to student referendum to be held November 28 - December 2, 2011.

Architect: Robertson Sherwood Architects in association with RDG Planning & Design

Construction Manager/General Contractor: TBD

Project Planner: Gene Mowery, Campus Planning and Real Estate, (541) 346-5593
Emily Eng, Campus Planning and Real Estate, (541) 346-5606

Construction Project Manager: Charlene Lindsay, Facilities Services, (541) 346-5503

 
Project Description  
The SRC Expansion and Renovation project is envisioned as a facility that meets the increasing needs for student recreation and academic programming. The project includes a new natatorium for aquatics recreation, fitness, and education; new or expanded locker rooms; additional cardio and weight-training space; a gymnasium and multipurpose athletic courts; additional multi-purpose space for programming and classes; social and study space with juice bar (or other healthy eatery) and pro shop; and public spaces commensurate with a major university building and campus recreation center adequate to support high-volume daily use. Expansion of the existing Student Tennis Center from 6 courts to 8-10 courts may be included as funding allows or as an additional phase of the project.
 