| [School of] Music and Dance Additions & Alterations |
|
 |
|
| |
|
| Current Status |
|
Construction |
|
| Project Timeline |
|
June 2006: E-Board authorized additional gift funding ($2,000,000)
November 2, 3006: Groundbreaking
December 2006: Selection of Contractor
April 2007: Construction began
Fall 2008: Anticipated occupancy
|
|
| Project Summary |
|
Location: MarAbel B. Frohnmayer Music Building, 961 E. 18th
Size: Renovation of 15,000 gsf and 29,000 gsf of new construction
Legislative Authorization:2001 Legislature — SB 5525 ($15,200,000); June 2006 Emergency Board ($2,000,000)
Expenditure Limitation: $17,200,000 ($7,600,000 G-bonds; $9,600,000 gifts)
Total Project Budget: $17,200,000
Architect: BOORA Architects, Portland
Construction Firm: John Hyland Construction, Inc., Springfield
Project Planner: Dorene Steggell, University Planning Office, 6-5606
Project Manager: George Bleekman, Facilities Services, 6-2625
|
|
| Project Description |
|
The School of Music has begun design of its $17,000,000 project which will renovate 15,000 gsf and add 29,000 gsf of new construction. The project is intended to meet the immediate needs of the School for teaching, practice, rehearsal, recording, faculty studios, offices, and administration, as well as allowing for efficient future additions to the building. The project also will include needed utilities upgrades in the area and site development. |
|
| Links |
|
Project Description, June 2005 (PDF)
Capital Project document (PDF)
MarAbel B. Frohnmayer Music Building and Beall Hall ("The Architecture of the University of Oregon: A History, Bibliography, & Research Guide")
University of Oregon Historic Property Index (PDF)
|
|
| |
|
| Back to Top |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|