Hayward Field Improvements  
 
   
Current Status  
Under Construction
 
Project Timeline  

June 2006: Emergency Board authorization

October 2006: Construction began

Winter 2008: Completion

 
Project Summary  

Location: 15th Avenue and Agate Street

Legislative Authorization: Emergency Board, June 2006; 2007 Legislature SB 5516

Expenditure Limitation and Total Project Budget: $7,390,000 + $5,000,000 = $12,390,000 ($2,500,000 G-bonds + $9,890,000 gifts).

Architect: Thompson Vaivoda & Associates, Portland

Construction Firm: McKenzie Commercial Contractors, Eugene

Project Planner: Chris Ramey, University Planning Office, 6-5562

Project Manager: Janet Lobue, Facilities Services, 6-5259

 
Project Description  

This $7.4 million project will put in place improvements needed to host the 2008 Olympic track and field trials at Hayward Field. A part of this project includes a longer term look at the future needs of the track-and-field program and how these can be met in the Hayward Field area.

 